Blue Rock Crushing | Talison Lithium Project
Case Details
Clients: Talison Lithium Pty Ltd
Location: Greenbushes
Scope: Produce 50,000m3 of 300mm minus blue rock
Equipment: Jaw Crusher, 36t Excavator, Stacker
Period: 2024
Let’s Work Together
Call us directly, or email us!
Address Business
49 Munday Avenue Pinjarra WA
Contact With Us
Call us: (08) 9531 3111
(08) 9531 3444
admin@peelresource.com.au
PO Box 222 Pinjarra WA 6208
(08) 9531 3444
admin@peelresource.com.au
PO Box 222 Pinjarra WA 6208
Delivering Precision Crushing Solutions for Talison Lithium’s Greenbushes Expansion
Peel Resource Recovery has been selected as the trusted crushing partner for Talison Lithium Pty Ltd at their Greenbushes operations, the world’s largest hard-rock lithium mine. In 2024, we undertook a critical project to produce 50,000 cubic meters of 300mm minus blue rock – a key material supporting Talison’s major site expansion and infrastructure development.
Project Scope
Our team was tasked with delivering:
- High-volume production of 300mm minus blue rock (exceeding 50,000m³)
- Strict quality control to meet Talison’s exacting specifications
- Continuous operations to align with the mine’s expansion timeline
- Safe material handling in an active mining environment
Our Operational Approach
To meet these challenges, we deployed a specialized crushing train:
Primary Reduction
36-tonne excavator feeding raw blue rock, and a Heavy-duty jaw crusher for initial size reduction.
Precision Processing
Secondary crushing to achieve consistent 300mm minus specification, and On-site quality testing of all processed material.
Efficient Stockpiling
Radial stacker system for rapid material placement, and Segregated stockpiles for quality assurance.